Downtown Fenelon Reconstruction

diggin' downtown fenelon falls

Downtown Fenelon Falls is open!

Fall in love with Fenelon Falls.

The summer might be over, but there's still lots to do in and around Downtown Fenelon Falls. Layer up this fall, grab your favourite hot beverage and head over to a nearby park, visit the trails along the locks, check out the new attractions and shop the downtown.

#diggindowntownfenelonfalls

Fenelon Falls is currently undergoing a reconstruction of the downtown area on Colborne Street, between Water Street and Bond Street West. This page will provide you with the latest information on construction and Diggin' Downtown Fenelon Falls, a campaign to help give local businesses a boost during the reconstruction project.

While construction and COVID-19 present short-term challenges, businesses continue to serve the community. There are still a variety of convenient ways to shop and businesses remain open for curbside pick-up or delivery and with social distancing protocols in place. Please reach out to a local business directly to check their availability.

This essential work to our roads and underground infrastructure will provide a needed revitalization to Fenelon Falls' Downtown that will benefit the community and businesses for many years to come. Meanwhile to support businesses during construction, Diggin' Downtown Fenelon Falls will highlight businesses in the construction area and help shoppers navigate around the construction.

Follow along in the coming months as we share updates and take part by sharing your shopping experiences in the downtown using #diggindowntownfenelonfalls. Stay home, stay safe and support local!

Business Support and Strategies

Tips to support your business to thrive in the midst of construction.

Business Support
We're in this together.

Downtown construction projects present short-term challenges, but Kawartha Lakes is committed to supporting your business while infrastructure improvements are made that will benefit us all in the long-term.

 Business info and resources

Communication is key for staying connected during construction.

  • Sign up for the Monday Construction Update, a week-by-week update on the construction, by contacting carbour@kawarthalakes.ca
  • Find up to date info at kawarthalakes.ca/diggindowntownfenelonfalls
  • Stay informed and prepared, by visiting kawarthalakes.ca/ecdevnews for newsletters, resources, blogs and events. Business support resources are readily available and updated frequently.
 Diggin' Downtown Fenelon Falls
Diggin’ Downtown Fenelon Falls is a marketing and placemaking campaign to raise awareness for Downtown Fenelon Falls and to encourage shoppers to support businesses in the construction area.
 Get your business online
  • The Digital Main Street program provides expert support for businesses interested in technologies. Get access at digitalmainstreet.ca
  • Sign up for shopHere at for your business online and to receive online training at no cost
  • Need help to improve your online presence? Click here to schedule a consultation with the Digital Service Squad.
  • The Storefront to Online (S2O) Program is designed to teach traditional brick and mortar, home-based businesses and not-for-profit agencies how to expand online.
  • The Recovery Action Program (RAP) is a fully-funded immersive training, mentoring and support program with digital modernization.
 Million Dollar Makeover
The Million Dollar Makeover is a funding program designed to encourage and support economic development in Kawartha Lakes. Get access to grants and loans to improve the visual and functional aspects of your commercial, mixed-use commercial/residential or heritage designated residential buildings.
To learn more, visit
kawarthalakes.ca/makeover.
Business Support Contacts

Carlie Arbour, City of Kawartha Lakes

Economic Development Officer, Community + Downtowns

705-324-9411 extension 1396

carbour@kawarthalakes.ca

 

Marylee Boston, Fenelon Falls & District Chamber of Commerce

Manager

705-887-3409

members@explorefenelonfalls.com

 Essential Business Strategies
 Here are some tips to support your business to thrive in the midst of construction.
Keep customers and vendors informed

Help ensure that your customers have the opportunity to access parking.

  • Inform your customers of the closest parking lots
  • Inform vendors or delivery agencies of changes to road access
  • Encourage staff to park in lots outside of the downtown core
 Meet your customers online

Ensure you have multiple channels for your customers to find and know what you have available, especially during COVID-19. Here are a few suggestions:

  • Research Online, Purchase Offline: Customers are researching products online, then purchasing in store. Use your online space to show them your offering and what’s available.
  • Buy Online, Pick-up In Store: Offering Pick-up In Store and Curbside allows you to make the sale and customers to feel safe while browsing online, particularly during COVID-19.
  • Get creative and find alternate ways to bring your product to your customer. Options include home delivery, pick-up models, meetings or consultations.
  • Get set-up with an online store for free with shopHERE.
 Keep a positive customer experience
Invite your customers to visit often during construction so they see progress in real-time. Customers will remember your opinion of the construction and your excitement will leave them wanting to come back.
 Enhance your marketing

Look at your overall marketing strategy - is it doing what you need? Maybe it’s time to update your approach.

  • Visit digitalmainstreet.ca for free resources and training tutorials to help you build a digital plan
  • Kawartha Lakes has hired a Digital Service Squad to help businesses with free digital consulting, book your free session today.
Be creative to attract customers
  • Host promotions or events for your customers, try limited time items, new products or weekly specials and announcements.
  • Be creative and don’t forget to share your promotions on social media, follow @EcDevKL and use #diggindowntownfenelonfalls
Brighten your storefront
  • Bring new colour to your window displays to draw attention and brighten the customer experience.
  • Apply for funding for an upgrade at kawarthalakes.ca/makeover
Collaborate with your neighbours
  • Look for ways to cross-promote events and sales with other businesses, even those outside the construction area.
  • Consider collaborative discounts, coupons or complimentary events

About the reconstruction project

The municipality of Kawartha Lakes, through their consultant Ainley Graham & Associates Limited (Ainley Group) is undertaking the detailed design for the reconstruction of Colborne Street in the community of Fenelon Falls. The project involves full road reconstruction including watermain, storm sewer, and sanitary sewer replacement, new curb and gutter and streetscape improvements.

What?

Road reconstruction:

  • Between Bond Street and Water Street
  • Underground replacement of storm sewer, sanitary sewer and watermain
  • Concrete curb and gutter work
  • Dedicated right and left turn lanes added
  • New furnishing and pedestrian walkways

Why?

Did you know that the infrastructure in downtown Fenelon is over 60 years old? That means that the underground utilities, such as the storm sewer, sanitary sewer and watermain systems are outdated and need replacing. At the same time, we are taking the opportunity to address the road, sidewalk, landscaping and walkability features of the area.

Project details

Please click on the headings below for more information on the Downtown Fenelon Reconstruction Project.

Additionally, you can follow us on social media, subscribe to our newsroom or download our municipal app Pingstreet to receive road closures and information straight to your phone.
Weekly updates

Week of November 1

  • Traffic light work at Francis St. and Colborne St. will continue all week.
  • Brick paver and planter installation to continue all week.
  • Two way traffic will remain in both directions for the week. Minor flagging operations may take place as required for equipment setup or deliveries.
  • Some parking stalls along both blocks will be occupied to allow workers to access the sidewalk and boulevard areas to complete their work.

Week of October 25

  • Traffic light work at Francis St. and Colborne St. will continue all week.
  • Brick Paver and planter installation to continue all week.
  • Two way traffic will remain in both directions for the week. Minor flagging operations may take place as required for equipment setup or deliveries.
  • Some parking stalls along both blocks will be occupied to allow workers to access the sidewalk and boulevard areas to complete their work.

Week of October 18

  • Traffic light work at Francis St. and Colborne St. will continue all week.
  • Brick paver and planter installation to continue all week.
  • Two way traffic will remain in both directions for the week. Minor flagging operations may take place as required for equipment setup or deliveries.
  • Some parking stalls along both blocks will be occupied to allow workers to access the sidewalk and boulevard areas to complete their work.

Week of October 11

  • Traffic light work at Francis St and Colborne St. will continue all week.
  • Brick paver installation will resume and continue all week.
  • Two way traffic will remain in both directions for the week. Minor flagging operations may take place as required for equipment setup or deliveries.
  • Some parking stalls along both blocks will be occupied to allow workers to access the sidewalk and boulevard areas to complete their work.

Week of October 4

  • Traffic light work will continue at Colborne St. and Francis St. all week.
  • Two way traffic will remain in both directions for the week. Minor flagging operations may take place as required for equipment setup or deliveries.
  • Some parking stalls along both blocks will be occupied to allow workers to access the sidewalk and boulevard areas to complete their work.

Week of September 27

  • Traffic light work to begin at Colborne St. and Francis St. mid week.
  • Paving stone installation to continue all week.
  • Two way traffic will remain in both directions for the week. Minor flagging operations may take place as required for equipment setup or deliveries.
  • Some parking stalls along both blocks will be occupied to allow workers to access the sidewalk and boulevard areas to complete their work.

Week of September 20

  • Traffic light work to begin at Colborne St. and Francis St. mid week.
  • Paving stone installation to continue all week.
  • Two way traffic will remain in both directions for the week. Minor flagging operations may take place as required for equipment setup or deliveries.
  • Some parking stalls along both blocks will be occupied to allow workers to access the sidewalk and boulevard areas to complete their work.

Week of September 13

  • Street lighting work will continue all week
  • The temporary street lighting will remain operational until at least one side of the street has permanent street lighting energized.
  • Paving stone installation will begin and continue all week.
  • Two way traffic will remain in both directions for the week. Minor flagging operations may take place as required for equipment setup or deliveries.
  • Some parking stalls along both blocks will be occupied to allow workers access to the sidewalk and boulevard areas to complete their work.

Week of September 6

  • Coco Paving and our electrical sub contractor (TM3) will be on site to begin installing the permanent street lighting.
  • The temporary street lighting will remain operational until at least one side of the street has operational permanent lighting.
  • Two way traffic will remain in all directions for the week. Minor flagging operations may take place as required for equipment setup or deliveries but will be kept to a minimum.
  • Some parking stalls along both blocks will be required to allow workers access to the sidewalk and boulevard areas to complete their work.
  • Coco Paving will begin removing the gravel in the boulevard in preparation of the new paving stone installation beginning the following week.

Week of June 21

  • Colborne St. – Water St. to Bond St.
  • Construction in these two blocks is completed for Spring 2021
  • Work will be on hold until after Labour Day Weekend.
  • June 28 to August 26:
    A secondary portion of the Colborne St. Reconstruction Project consists of various repairs of the underground storm water tunnel crossing Colborne St.
  • The concrete crews will be in town to complete this work however, as all the work is completed below the buildings and streets very minor disturbance is expected to residents and businesses. Access to the tunnel will be by manholes and culverts so crews and equipment may congregate near these access points to complete the work inside it.

Week of June 14

  • Colborne St. – Water St. to Bond St.
  • Paving of the second lift of base asphalt.

  • Temporary Line Marking

  • General Cleanup

  • Remove Temporary Construction fence

  • Reinstate Signage

  • Remove Traffic Detour

  • Demobilize until after Labour Day 2021

Week of June 7, 2021

  • General clean up

  • Placing of top granulars and grading for base asphalt

  • May be small patches of concrete being poured early in the week

  • Filling of voids in concrete where the future brick (fall 2021) is to be placed to make it safe for the summer

  • Paving of base asphalt (two lifts) will take place mid week

  • Temporary line painting will follow the base asphalt

  • Northbound traffic will remain through both blocks all week

  • Southbound traffic will remain detoured around both blocks for the week

Week of May 31, 2021

  • General clean up, raising catchbasins to asphalt grade, placing and grading top granulars in anticipation of paving the week of June 7
  • The electrical contractor will be installing the temporary street lights
  • Small patches of concrete will be poured throughout the week
  • Demobilizing of equipment and materials no longer required at this time
  • Northbound traffic will remain through both blocks all week
  • Southbound traffic will remain detoured around both blocks for the week

     

Week of May 24, 2021
Colborne St. Water St. to Bond Street

  • General clean up, flushing and video of the sewers, raising catchbasins to asphalt grade, placing and grading top granulars.
  • The electrical contractor will be installing the temporary street lights.
  • Demobilizing of various equipment no longer needed on the project.
  • Preparing to pave the base asphalt in the next couple weeks.
  • Northbound traffic will remain through both blocks all week.
  • Southbound traffic will remain detoured around both blocks for the week.


Week of May 17, 2021
Colborne St. Water St. to Bond Street

  • The crews will be cleaning up, adding granulars and grading for concrete curb and sidewalk.
  • Concrete curb and sidewalk will be poured in various locations in each block throughout the week.
  • Access to buildings throughout the week will be maintained as much as possible however minor interruptions may take place.
  • Northbound traffic will remain through both blocks all week.
  • Southbound traffic will remain detoured around both blocks for the week.

 

Week of May 10, 2021

Colborne St. Water St. to Bond Street

  • The underground crew will be completing the final watermain hookup at Francis St.
  • Any affected businesses or residents have been notified.
  • Misc. storm sewer and fire hydrant work to take place on the East side of Colborne St.
  • Road excavation and granular placement on the East side of Colborne St.
  • Concrete curb and sidewalk grading and pouring to take place all week in the block of Colborne St. between Water St. and Francis St. both sides of the street.
  • Northbound traffic will remain through both blocks all week.
  • Southbound traffic will remain detoured around both blocks for the week.


Week of May 3, 2021
Colborne St. (Water St. to Francis St.)

  • The crew in this block will be completing the sanitary sewer and one watermain hookup in the Francis St. intersection.
  • No resident or business will be out of water during the watermain connection.
  • Concrete removals and service installation will also be taking place throughout the week on the East side of this block.

 

 Colborne St. (Water St. to Francis St.)

  • The second crew will be in this block completing hydro conduits
  • Forming and pouring the box culvert tunnel
  • Installing ground plates and cleaning up and preparing to grade for curb
  • Northbound traffic will remain through both blocks all week.
  • Southbound traffic will remain detoured around both blocks for the week.


Week of April 26, 2021

Colborne St. (Francis St. to Bond St.)

  • The crew in this block will continue to install storm sewer for most of the week on the West side of the block.
  • Southbound traffic will remain detoured around Colborne St. all week

Colborne St. (Water St. to Francis St.)

  • The second crew will finish up the road excavation and granular placement on the West side of the Street.
  • During the day on Wednesday the crew will flip to the East side of this block and continue to install water and sanitary services to the buildings.

  • Concrete removals on the East side will take place for the second half of the week to install the services.

  • Small sections of the sidewalk will be closed temporarily to install the services.

  • Traffic will remain Northbound through the block.

  • Southbound traffic will remain detoured for the entire week.


Week of April 19, 2021

Colborne St. (Francis St. to Bond St.)

 

  • The crew in this block will continue to install storm sewer for most of the week on the West side of the block.
  • Southbound traffic will remain detoured around Colborne St. all week

 Colborne St. (Water St. to Francis St.)

  • The second crew will finish up the road excavation and granular placement on the West side of the Street.
  • During the day on Wednesday the crew will flip to the East side of this block and continue to install water and sanitary services to the buildings.
  • Concrete removals on the East side will take place for the second half of the week to install the services.
  • Small sections of the sidewalk will be closed temporarily to install the services.
  • Traffic will remain Northbound through the block.
  • Southbound traffic will remain detoured for the entire week.


Week of April 12, 2021

Colborne St. (Francis St. to Bond St.)

  • One crew will complete a watermain cut and cap and install the remainder of the watermain within the Francis St. intersection.
  • Some residents and businesses may be temporarily out of water during the cut and cap on Monday (Notices have already been handed out to the affected buildings)
  • The Southbound traffic will remain detoured around Colborne. St. for the week.
  • Once the work in the intersection is complete the crew will move to begin storm sewer installation on the West side of this block for the remainder of the week.

 

Colborne St. (Water St. to Francis St.) 

  • The second crew will complete concrete removals all week while sanitary services are installed on the West side of this block.
  • Storm sewer installation will also take place during the week on the same side of the block.
  • Parts of the sidewalk on West side will be closed temporarily in small sections to install the sanitary services.
  • Southbound traffic will remain detoured around this block as well for the week.


Week of April 5, 2021

Colborne St. (Francis St. to Bond St.)

  • Continue installing sanitary sewer and watermain heading North from Francis St. towards Bond St.
  • Installing new sanitary and water services on the West side of this block.
  • Parts of the sidewalk on the West side will be closed temporarily in small sections to install the services.
  • The Southbound traffic will remain detoured around Colborne St. for the week.

 

Colborne St. (Water St. to Francis St.)

  • Concrete removals and water service installation will occur all week on the West side of this block.
  • Minor water interruptions may occur while connecting the new water services to the existing plumbing within the buildings.
  • Notification will be given 24 hours prior to this brief switch over for each individual building.
  • Parts of the sidewalk on the West side of this block will be closed temporarily in small sections to install the services.
  • Southbound traffic will remain detoured around this block for the week.



Week of March 29, 2021

Colborne St. (Francis St. to Bond St.)

  • Continue installing sanitary sewer as well as watermain heading North from Francis St. towards bond with main line crew.
  • Installing new sanitary services on the West side of this block during the week as well.
  • Parts of the sidewalk will be temporarily closed in small sections to install the sanitary services
  • The Southbound traffic will remain detoured around Colborne St. for the week.

 

Colborne St. (Water St. to Francis St.)

  • A second crew will be on site to complete a watermain connection at Water St. and Colborne St.
  • Concrete removals and water service installation will occur all week on the West side of the street.
  • Minor water interruptions may occur while connection the new water services to the exiting plumbing within the buildings.
  • Notification will be given 24 hours prior to this brief switch over for each individual building.
  • Parts of the West sidewalk will be closed temporarily in small sections to install the water services.
  • Southbound traffic will remain detoured around this block of Colborne St. for the week.

 

Week of March 22, 2021

  • Colborne St. Water St. to Francis St.: The watermain within this block will be under test for the entire week prior to final hookups. Ongoing backfill operations and concrete removals will take place throughout the week. The Southbound traffic will remain detoured around Colborne St.
  • Colborne St. Francis St. to Bond St.: The intersection of Francis St. will be closed to all but Northbound traffic in order to install the sanitary sewer manhole in the middle of the intersection. We anticipate this intersection to remain closed as described for the remainder of the week to allow the watermain and sanitary sewer installations across it.
  • Southbound traffic on Colborne St. will be detoured via Bond St. W./Market St./May St. and Water St.
  • Following, they will begin pulverizing the existing asphalt and installing pedestrian safety fence and signage.
  • Watermain and sanitary sewer installation will also continue north from Francis St. to Bond St. for the remainder of the week.

Week of March 15, 2021

  • The crews will continue installing sanitary sewer and watermain heading North from Water St. heading towards Francis St.
  • The traffic control and detour will remain in effect for the week.

 

Week of March 8, 2021

  • Crews will begin installing sanitary sewer and watermain at Colborne St. and Water St. heading North towards Francis St.
  • The traffic control and detour will stay in effect for the week.

Week of March 1, 2021

  • Set up traffic detour around the block of Colborne St. between Francis St. and Water St.
  • Construction safety fence will be put up within this block to delineate the work zone from the single travel lane and the pedestrian zones.
  • Excavate test pits in the roadway
  • Continue to mobilize the site
  • Moving in equipment and materials
  • Daylighting of underground utilities
  • Pulverize the existing asphalt on Colborne St. between Water St. and Francis St.
  • Cut and Cap watermain at Water St. and Colborne St.
  • Local water outages will occur, notices will be handed out ahead of time
  • Continue to prepare to start sanitary sewer excavation
 Project phases

The project will be completed in two phases, taking place in the spring and in the fall of 2021, with a break in the summer months. The first phase will take place between March and May 2021. The second phase will resume Labour Day weekend in September and is expected to be completed by the late fall. 

Map of constructiion zone in Fenelon Falls

 Public meetings
 The first public meeting was held on May 23, 2019 at the Fenelon Falls Arena.


The second public meeting was held on October 2, 2019 at the Fenelon Falls Arena.

 Project contacts
John Innes, C.E.T.

City of Kawartha Lakes
Infrastructure Design and Construction
Engineering and Corporate Assets

705-324-9411 extension 1164

jinnes@kawarthalakes.ca

Contact Us