Week of November 1 |
- Complete remaining landscaping works on Cambridge St (private walkways included)
- Locate Town Clock Wire (repair to be facilitated by Sub Contractor at a later date)
- Open Cambridge St S
- Rubberized Mulch (Weather Dependent)
- Line Painting – Kent & Cambridge St (Night)
- Rubberized Mulch (Weather Dependent)
|
Week of October 25 |
- Pave remaining driveways on Cambridge St
- Rubberized Mulch in Tree Pits
- Line Painting – Kent & Cambridge St
|
Week of October 18 |
- Grade Cambridge St for asphalt
- Prep Pie Eyed Monk Alley Way for asphalt
- Prep Police Station for asphalt
- Power Supply Install
- Pave Cambridge St S
- Pave All Driveways and alleyways
|
Week of October 11 |
- Landscape restoration - Cambridge St S
- Interlock Installation – Cambridge St S
- CCTV Laterals – Cambridge St S
- Grade Cambridge St S
- General Site Cleanup Before Weekend
- Sign Install – Cambridge St S
|
Week of October 4 |
- Landscape restoration - Kent & Cambridge St S
- Plant Trees - Cambridge St S (weather permitting)
- Interlock brick Cambridge St S
- Driveway grading and prep
- Rubberized mulch application in tree pits
- Interlock placement along Cambridge St S
- General Clean-up and safety prevision review ahead of Thanksgiving weekend.
|
Week of September 27 |
- Deficient concrete repair - Cambridge St. S.
- Plant Trees - Kent St (weather permitting)
- Interlock brick placement - Cambridge St. S.
- Driveway and walkway grading - Cambridge St. S.
- Landscape and cleanup - project wide.
|
Week of September 13 |
- Prepping Sidewalk & Undermat – Cambridge St S
- Asphalt Samples for Referee Test
- Setup Forms for Concrete Sidewalk & Undermat - Cambridge St S
- Plant Trees - Kent St (weather permitting)
- Pouring Concrete Sidewalk & Undermat- Cambridge St S
- Adjust Aluminum Brackets in planters
|
Week of September 6, 2021 |
- Prepare and setup forms for concrete sidewalk and brick under mat - Cambridge St S
- Plant Trees - Kent St (weather permitting)
- Pouring concrete sidewalk and under mat- Cambridge St S
|
Week of August 23, 2021 |
- Sanitary lateral repairs – Cambridge South
- Sidewalk Preparation – Cambridge South
- Interlock installation – Kent St between Cambridge and Victoria
- Sidewalk pour – Cambridge South
- Fine grading – Cambridge South
- Catch Basin and maintenance hole adjustments – Cambridge South
- Sidewalk pour – Cambridge South
- Streetlight Pole installation – Cambridge South
- Back of sidewalk restoration – Cambridge South
- Power supply installation – Cambridge North
- Back of sidewalk restoration – Cambridge South
- Power supply installation – Cambridge North
- Interlock installation – Kent St between Cambridge and Victoria
|
Week of August 16, 2021 |
- Stringline for curb installation – Cambridge St South
- Interlock installation – Kent St between Cambridge and Victoria
- Stringline for curb grading – Cambridge St South
- Curb installation – Cambridge St South
- Fine Grading – Cambridge St South
- Streetlight Pole Installation – Cambridge St South
- Structure Adjustments – Cambridge St South
- Paving – Cambridge St South
- Sidewalk installation – Cambridge St South
- Back of walk restoration – Cambridge St South
|
Week of August 9, 2021 |
-
Stringline installation – Cambridge South
-
Sidewalk prep – Cambridge South
-
Interlock installation – Kent St between Victoria and Cambridge
-
Curb installation – Cambridge South
-
Streetlight installation – Cambridge South
-
Sidewalk prep – Cambridge South
-
Fine grading – Cambridge South
-
Fine grading – Cambridge South
-
Adjustments – Cambridge South
-
Paving – Cambridge South
-
Restoration – Cambridge South
|
Week of August 2, 2021 |
- Interlock installation – Kent St between Cambridge and Victoria
- Stringline installation - Cambridge South
- Curb installation - Cambridge South
- Fine Grading - Cambridge South
- Adjustments – Cambridge South
|
Week of July 26, 2021 |
- Removal of temporary watermain – Cambridge South
- Interlock installation – Kent St between Cambridge and William
- Watermain connection – Cambridge South
- Street lighting conduit installation – Cambridge South
- Preparation for curb installation – Cambridge South
- Stringline installation – Cambridge South
- Interlock installation – Kent St between Cambridge and Victoria
- Curb installation – Cambridge South
|
Week of July 19, 2021 |
-
Granular B Placement – Cambridge South
-
Granular A Placement – Cambridge South
-
Subdrain installation – Cambridge South
-
Interlock installation – Kent St between Cambridge and William
-
Tree pit installation – Kent St between Cambridge and Victoria
-
New Water Service Connections – Cambridge South
-
Interlock installation – Kent St between Cambridge and William
-
Watermain Connection – Cambridge South
-
Street lighting conduit installation – Cambridge South
|
Week of July 12, 2021
|
- Watermain connections – Cambridge South
- Water service connections – Cambridge South
- Curb placement – Cambridge South
- Street lighting installation – Cambridge South
- Granular A placement – Cambridge South
- Interlock installation – Kent St between Cambridge and William
- Interlock installation – Kent St between Cambridge and Victoria
|
Week of July 5, 2021
|
- Hardco will be reinforcing tree pits this week.
- Road excavation – Cambridge South
- Watermain commissioning – Cambridge South
- Watermain removal – Cambridge South
- Interlock installation – Kent St between Cambridge and William
- Sidewalk removals – Cambridge South
- Subdrain installation – Cambridge South
- Granular B Placement – Cambridge South
- Street lighting conduit installation – Cambridge South
- Granular A Placement – Cambridge South
- Sidewalk preparation – Cambridge South
- Interlock installation – Kent St between Cambridge and William
|
Week of June 28, 2021 |
-
Water service installation – Cambridge St South
-
Interlock installation – Kent St between Cambridge and William
-
Catchbasin installation – Cambridge St South
|
Week of June 21, 2021 |
-
Watermain installation – Cambridge St South
-
Interlock installation – Kent St between Cambridge and William
-
Water service installation – Cambridge St South
|
Week of June 14, 2021 |
-
Sanitary lateral installation – Cambridge Street South
-
Interlock installation – Kent St between William and Cambridge
-
Watermain installation – Cambridge Street South
|
Week of June 7, 2021 |
-
Sanitary lateral install – Cambridge South
-
Interlock placement – Cambridge North
-
Tree pit installation – Kent St between William and Cambridge
-
Concrete undermat at radii – Kent St at Cambridge
-
Preparing for undermat at radii – Kent St at Cambridge
-
Sanitary lateral install – Cambridge South
-
Lawn restoration – Cambridge North
-
Interlock placement – Kent St between William and Cambridge
-
Watermain installation – Cambridge South
-
Water service installation – Cambridge South
-
Interlock installation – Kent St between William and Cambridge
-
Tree pit install – Cambridge North
|
Week of May 31, 2021 |
- Tree pit installation – Kent St between William and Cambridge
- Pouring undermat for interlock – Kent St between Victoria and Cambridge
- Cut and Cap watermain – Cambridge South
- Sanitary sewer install – Cambridge South
- Pour parking lot driveway – Cambridge North
- Sanitary lateral installation – Cambridge South
- Interlock installation – Kent St between William and Cambridge
- Watermain installation – Cambridge South
-
Raise Manhole Frames and Covers
-
Place surface Asphalt in the Evening
-
Line Paint
-
Tidy up signs and barrels
|
Week of May 25, 2021 |
- Set up traffic control – Kent St
- Set up traffic control – Cambridge South
- Finalize temporary watermain – Cambridge South
- Concrete undermat pour – Kent St between William and Cambridge (
- Prep for concrete undermat – Kent St between William and Cambridge
- Strip forms from planters – Kent St between William and Cambridge (IPac)
- Tree pit installation – Kent St between William and Cambridge (All Seasons)
- Streetlight installation – Kent St between Victoria and Cambridge (Guild)
- Close Cambridge St South
- Open Kent St to two way traffic
- Cut and cap watermain – Cambridge South *Need water shutdown, no one affected as all will be on temporary water*
- Landscape and restoration – Cambridge North
- Pedestrian crossover installation – Kent St between William and Cambridge
- Interlock installation – Kent St between William and Cambridge (All Seasons)
|
Week of May 17, 2021 |
- Construct planters – Kent St between William and Cambridge
- Pour undermat – Kent St between William and Cambridge
- Interlock sample laying – Kent St between William and Cambridge
- Sanitary lateral repairs – Kent St between William and Cambridge
- Street lighting installation – Kent St between Cambridge and Victoria
- Sodding – Victoria intersection
- Tree pit installation – Kent St between William and Cambridge
- Street lighting installation – Kent St between Cambridge and Victoria
*Holiday Monday for Victoria Day*
|
Week of May 10, 2021 |
- Planter construction – Kent between Cambridge and William
- Standing street lighting poles – Kent between Cambridge and William
- Boulevard restoration – Victoria Intersection
- Sidewalk pouring – Victoria Intersection
- Sidewalk pouring – Cambridge North
- Concrete undermat Pour – Kent between Cambridge and William
- Sample Brick Area – Kent between Cambridge and William *Tentative, to be confirmed*
- Tree pit install – Kent between Cambridge and William
- Standing street lighting poles – Kent between Cambridge and Victoria
- Concrete Undermat Pour – Kent between Cambridge and Victoria
- Tree pit install – Kent between Cambridge and William
- Interlock install – Kent between Cambridge and William
- Landscaping – Kent between Cambridge and William
- Sidewalk and concrete driveway install – Cambridge North
|
Week of May 3, 2021 |
- Fine grading granular A ahead of paving – Kent between West Limit and Cambridge
- Adjustments of manholes, catchbasins, and valves ahead of paving – Kent between West Limit and Cambridge
- Standing traffic poles – Victoria Intersection (Guild)
- Concrete underlay forming and pouring – Kent between Cambridge and William
- Paving base asphalt – Kent St between West Limit and Cambridge
- Standing street lighting poles – Kent St between Victoria and Cambridge
- Line painting – Kent St at Victoria Intersection
- Fine grading granular A ahead of paving – Kent St between Cambridge and William
- Adjustments of manholes, catchbasins, and valves ahead of paving – Kent St between Cambridge and William
- *Open Victoria Intersection*
- *Close Cambridge Intersection*
- Standing street lighting poles – Kent St between Victoria and Cambridge
- Paving base asphalt – Kent St between Cambridge and William
- Fine grading granular A ahead of paving – Cambridge between Kent and Peel
- Adjustments of manholes, catchbasins, and valves ahead of paving – Cambridge between Kent and Peel
- Installation of conduit for fibre – Cambridge between Kent and Peel
- Standing street lighting poles – Kent St between Victoria and Cambridge
- Concrete underlay forming and pouring – Kent between Cambridge and William
- Paving base asphalt – Cambridge between Kent and Peel
- Line painting – Kent and Cambridge
- Standing street lighting poles – Kent St between Cambridge and William
- Sidewalk forming and pouring – Cambridge between Kent and Peel
- Sidewalk prep – Cambridge between Kent and Peel
|
Week of April 26, 2021 |
- Hard surface removals and grading boulevards – Kent St between Cambridge and William
- Concrete underlay construction – Kent St between Cambridge and William
- Pulling electrical cable – Kent St between Cambridge and Victoria
- Stringline for curb – Cambridge North
- Grading granular A – Cambridge North
- Pulling street lighting cable – Kent St between Cambridge and William
- Place curb – Cambridge North
- Trench Drain Installation – Kent St between Cambridge and William
- Fine grading – Cambridge North
- Concrete Undermat Construction - Kent St between Cambridge and William
- Structure Adjustments – Kent St between Cambridge and William
- **Open Cambridge Intersection**
- **Close Victoria Intersection **
- Remove asphalt – Victoria and Kent
- Road excavation – Victoria and Kent
- Granular B placement – Victoria and Kent
- Stand traffic signal poles – Victoria and Kent
- Planter box construction – Kent St between Cambridge and William
|
Week of April 19, 2021 |
- Grade boulevards for concrete underlay (north & south) - Kent St between Cambridge and William
- Fine grade A with grader prior to asphalt - Kent St between Cambridge and William
- S&I Electrical wiring – Kent St Victoria to William (Guild)
- Install Traffic signal poles – Kent and Victoria intersection (Guild)
- Watermain testing for 150mm – Cambridge North
- Connect hydrant lead – Cambridge North
- Install electrical ducts – Cambridge North
- Fine grade A ahead of asphalt – Cambridge North
|
Week of April 12, 2021 |
- Complete hard surface removals, grade boulevards for Concrete Underlay (North) - Kent St between Cambridge and William
- Storm sewer install
- Sanitary lateral install
- Supply and place traffic signal pole base and pour traffic controller Pads @ Cambridge Intersection
- Planter box construction – Kent St between Cambridge and William
- Pour traffic controller pads at Victoria Intersection
- Road excavation – Cambridge North
- Install subdrain – Cambridge North
- Place Granular B – Cambridge North
- Watermain testing for 150mm – Cambridge North
- S&I Electrical wiring – Kent St Victoria to William
|
Week of April 5, 2021 |
- Install String Line – Kent St between Cambridge and William
- Fine Grade A for curb – Kent St between Cambridge and William
- Install new 50mm W/S to 183 Kent (The Grand) – Kent St between Cambridge and Victoria.
- Restore working area around new W/S install – Kent St between Cambridge and Victoria.
- Grade Boulevards for Concrete Underlay (South) - Kent St between Cambridge and Victoria.
- Fine Grade A – Kent St between Cambridge and Victoria.
- Install new 50mm W/S to 171 Kent (The Grand) – Kent St between Cambridge and Victoria.
- Restore working area around new W/S install – Kent St between Cambridge and Victoria.
- Grade Boulevards for Concrete Underlay (South) - Kent St between Cambridge and Victoria.
|
Week of March 22, 2021 |
- Continue water service connections – Kent St between Cambridge and William
- Grading and shaping boulevards – Kent St between Cambridge and William
- Install street lighting duct on the south side - Kent St between Cambridge and William
- Grading and shaping of boulevards – Kent St between Cambridge and Victoria
- Final watermain connection – Kent St at William St
- Watermain removal – Kent between Cambridge and William
- Preparation for curb installation with granular A placement – Kent St between Cambridge and Victoria
|
Week of March 15, 2021 |
|
Week of March 8, 2021 |
|
Week of March 1, 2021 |
- Water service installation on North side - Kent between Cambridge and William
- Continue 200mm sanitary sewer - Kent and Cambridge Intersection
- Resume water main installation - Kent and Cambridge Intersection
- Road excavation, sub drain installations & Granular B Placement - Kent between Cambridge and William
- Installation of duct work for street lighting – Kent between Cambridge and William
- Road widening excavation and sub-drain installation west of Victoria
- Installation of duct work for street lighting – Kent between Cambridge and Victoria
- Curb string line installations and prep – Kent between Cambridge and Victoria
- Placement of granular A for curb grade only – Kent between Cambridge and Victoria
- Victoria intersection Traffic Signal Works (outside of traffic allowance)
|
Week of February 22, 2021 |
Tuesday February 23
- Victoria intersection to be reopened to north/south traffic
- Cambridge intersection to be closed from south of Fire hall driveway, to North of optometrist driveway
- Water service installation on North side - Kent between Cambridge and William
- Intersection pulverizing - Kent & Cambridge
- Grading and shaping of granular B – Kent St between Cambridge and Victoria
- Installation of duct work for street lighting – Kent St between Cambridge and Victoria
Wednesday February 24
- Water service installation on North side - Kent between Cambridge and William
- Cut and Cap existing 200mm water main crossing Cambridge North side - Kent and Cambridge
- Removal of existing sanitary manhole – Kent and Cambridge
- Road widening excavation and subdrain install west of Victoria - Kent St between Cambridge and Victoria.
- Installation of duct work for street lighting – Kent St between Cambridge and Victoria.
- Preparation for curb - Kent between Cambridge and Victoria
Thursday February 25
- Water service installation on North side - Kent between Cambridge and William
- Begin 200mm Sanitary Sewer to SAN MH1 - Kent & Cambridge
- Road widening excavation and subdrain install west of Victoria - Kent St between Cambridge and Victoria
- Installation of duct work for street lighting – Kent St between Cambridge and Victoria
- Preparation for curb - Kent between Cambridge and Victoria
Friday February 26
- Water service installation on North side - Kent between Cambridge and William
- Continue 200mm sanitary sewer instal - Kent and Cambridge
- Road widening excavation and subdrain install west of Victoria - Kent St between Cambridge and Victoria
- Installation of duct work for street lighting – Kent St between Cambridge and Victoria
|
Week of February 15, 2021 |
Tuesday, February 16
- Continue water service installations – Kent between Cambridge and William
- Continue road excavation – Kent between Victoria and Cambridge
- Continue sub-drain installation – Kent between Victoria and Cambridge
Wednesday, February 17
- Continue water service installations – Kent between Cambridge and William
- Install temporary lighting connection overheads – Kent between Cambridge and William
- Continue road excavation – Kent between Victoria and Cambridge
- Continue sub drain installation – Kent between Victoria and Cambridge
Thursday, February 18
- Continue water service installations – Kent between Cambridge and William
- Complete temporary lighting activations – Kent between Cambridge and William
- 200mm water main connections – Kent between Victoria and Cambridge
- Water shut down required between 8am to 5pm – notices handed out Monday
- Continue road excavation – Kent between Victoria and Cambridge
- Continue sub drain installation – Kent between Victoria and Cambridge
Friday, February 19
- Continue water service installations – Kent between Cambridge and William
- Continue hard surface removals – Kent between Cambridge and William
- Continue road excavation – Kent between Victoria and Cambridge
- Continue sub drain installation – Kent between Victoria and Cambridge
|
Week of February 8, 2021 |
Monday February 8
- All work cancelled due to extreme cold temperatures
Tuesday February 9
- Water service installation along Kent, South side between Cambridge and William.
- Sanitary service installation along Kent, North side between Cambridge and William.
- Road excavation along Kent between Cambridge and Victoria.
- Water service transfer from North main to South main at CKL building.
- Temporary street lighting between Cambridge and William.
- Liquid Logics on site to start commissioning watermain near Victoria.
Wednesday February 10
- Water service installation along Kent, South side between Cambridge and William.
- Sanitary service installation along Kent, North side between Cambridge and William.
- Road excavation along Kent between Cambridge and Victoria followed by subdrain install.
- Victoria Avenue intersection electrical installation.
- Watermain commissioning.
Thursday February 11
- Water service installation along Kent, South side between Cambridge and William.
- Sanitary service installation along Kent, North side between Cambridge and William.
- Road excavation along Kent between Cambridge and Victoria followed by subdrain install.
- Victoria Avenue intersection electrical installation.
- Watermain commissioning.
Friday February 12
- Water service installation along Kent South between Cambridge and William.
- Sanitary service installation along Kent North between Cambridge and William.
- Granular B placement along Kent between Cambridge and Victoria.
- Victoria Avenue intersection electrical installation.
- Watermain commissioning.
|
Week of February 1, 2021 |
Monday, February 1
- Begin water service installations – Kent between Cambridge and William
- Continue North Side Lateral CIP Linings (East to West) – Kent between Cambridge and William
- Begin water main installations – Kent Street Starting at Victoria Avenue and heading West to Home Hardware
Tuesday, February 2
- Continue water service installations – Kent between Cambridge and William
- Continue North Side Lateral CIP Linings (East to West) – Kent between Cambridge and William
- Complete water main installations – Kent between Victoria and Home Hardware
- Excavate and prepare water main live taps – Kent between Victoria and Cambridge
Wednesday, February 3
- Continue water service installations – Kent between Cambridge and William
- Continue North Side Lateral CIP Linings (East to West) – Kent between Cambridge and William
- Begin 150mm Fire service installations – Kent between Victoria and Cambridge
Thursday, February 4
- Continue Water service installations – Kent between Cambridge and William
- Continue North Side Lateral CIP Linings (East to West) – Kent between Cambridge and William
- Investigation of existing Fixtures, connect temp street lighting – Kent between Cambridge and William
- Hard Surface Removals – Kent between Victoria and Cambridge
Friday, February 5
- Continue Water service installations – Kent between Cambridge and William
- Continue North Side Lateral CIP Linings (East to West) – Kent between Cambridge and William
- Investigation of existing Fixtures, connect temp street lighting – Kent between Cambridge and William
- Hard Surface Removals – Kent between Victoria and Cambridge
- Subgrade Excavation and Subdrain installations – Kent between Victoria and Cambridge
- Electrical Conduit installations – Kent between Victoria and Cambridge
|
Week of January 25, 2021 |
Monday, January 25
- Commence Intersection Closure – Victoria and Kent
- Storm Sewer installation – along Kent between Cambridge and William
- Complete North Side Sanitary Laterals excavation – Kent between Cambridge and William
- Complete Storm Laterals and CB installations - Kent between Cambridge and William
- Installation of temporary street lighting, installation of aerial feeds – Kent between Victoria and Cambridge
Tuesday, January 26
- Begin 300mm watermain installation – Kent between Cambridge to William
- Begin Sanitary lateral installation – Kent between Victoria and Cambridge
- Water Service installations/transfers along south businesses – Kent between Victoria and Cambridge
- Installation of temporary street lighting, installation of aerial feeds – Kent between Victoria and Cambridge
Wednesday, January 27
- Installation of temporary street lighting, installation of aerial feeds – Kent between Cambridge and William
- Continue watermain installation – Kent between Cambridge to William
- Begin Sanitary Lateral Lining long side Sewer Laterals to PL (east to west) – Kent between Cambridge and William
- Begin Storm Sewer Install – Kent between Victoria and Cambridge
- Continue Sanitary lateral installation – Kent between Victoria and Cambridge
Thursday, January 28
- Installation of temporary street lighting, installation of aerial feeds – Kent between Cambridge and William
- Continue watermain installation – Kent between Cambridge to William
- Continue Sanitary Lateral Lining long side Sewer Laterals to PL (east to west) – Kent between Cambridge and William
- Continue Storm Sewer Install – 300mm Storm sewer from STM MH 1 to MH 2 – Kent between Victoria and Cambridge
- Hydrant Relocation on south side @ Old Grand Building – Kent between Victoria and Cambridge
- Continue Sanitary lateral installations – Kent between Victoria and Cambridge
Friday, January 29
- Continue 300mm watermain installation – Kent between Cambridge to William
- Continue Sanitary Lateral Lining long side Sewer Laterals to PL (east to west) – Kent between Cambridge and William
- Complete Storm Sewer Install - Kent between Victoria and Cambridge
- Continue Sanitary lateral installations – Kent between Victoria and Cambridge
- Installation of temporary signal lights at Victoria – Kent at Victoria
|
Week of January 18, 2021 |
|
Week of January 11, 2021 |
Monday, January 11
- Install traffic control – Intersection of Cambridge and Kent
- Southbound Cambridge – Right turn only
- Northbound Cambridge – Closed at Kent
- Eastbound Kent – Right turns only
- Sanitary Sewer install (Within the Cambridge/Kent Intersection)
- Continue Sanitary sewer Laterals installations (South side)
Tuesday, January 12
- Sanitary Sewer install (Within the Cambridge/Kent Intersection)
- Continue Sanitary sewer Laterals installations (South side)
Wednesday, January 13
- Sanitary Sewer install (Within the Cambridge/Kent Intersection)
- Continue Sanitary sewer Laterals installations (South side)
Thursday, January 14
- Sanitary Sewer completion including temp cold patch restoration
- Continue Sanitary sewer Laterals installations (South side)
Friday, January 15
- Continue Sewer Installations (Friendly Dollar & Discount to Nisbett’s Clothiers)
- Continue Sewer Lateral installations
|
Week of January 4, 2021 |
Monday, January 4
- Mobilization
- Perimeter Fence installations – On Kent Street from William Street to Cambridge Street
Tuesday, January 5
Wednesday, January 6
- Sanitary Sewer install – starting on Kent Street at Cambridge Street and working towards William Street (South side of road)
- Sanitary lateral installations
Thursday, January 7
- Continue Sewer Installations
- Continue Sewer Lateral installations
Friday, January 8
- Continue Sewer Installations -Install San MH 3 (mid block, in front of Friendly Dollar & Discount)
- Continue Sewer Lateral installations
|