Week of July 24, 2023 |
King Street between James Street North and the Pigeon River Bridge:
- King Street will be open all week to normal traffic flow from James Street to the Pigeon River Bridge.
-
Ongoing electrical work, driveway asphalt replacement, concrete sidewalk placement and brick paving stone installation to take place throughout the week.
-
In general, all work will take place outside of the traveled portion of the roadway. Subcontractors will temporarily occupy on street parking spaces to access work zones.
King Street, Omemee (excluding the downtown portion)
|
Week of July 17, 2023 |
- King Street will be open all week to normal traffic flow.
-
Ongoing electrical work, concrete sidewalk placement and brick paving stone installation to take place throughout the week.
-
In general, all work will take place outside of the traveled portion of the roadway. Subcontractors will temporarily occupy on street parking spaces to access work zones.
|
Week of June 26, 2023 |
- West and East bound traffic on King Street will be directed through a single lane in the middle of the construction by temporary traffic lights.
- Additionally, there are three detours set up to detour traffic around the construction zone. Two detours are set up on Peace Road (one in each direction) and there is also a detour on Mary Street (eastbound only).
- Ongoing electrical work as well as concrete sidewalk pouring to take place all week.
- King Street will be open to normal traffic flow by end of day Friday June 30. Sturgeon Road North and SOuth will also be opened by the same deadline.
|
Week of June 19, 2023
|
- West and East bound traffic on King Street will be directed through a single lane in the middle of the construction by temporary traffic lights.
- Additionally, there are three detours set up to detour traffic around the construction zone. Two detours are set up on Peace Road (one in each direction) and there is also a detour on Mary Street (eastbound only).
- Ongoing electrical work, grading for sidewalk, placement of concrete sidewalk and boulevard work will take place all week.
|
Week of June 12, 2023
|
- West and East bound traffic on King Street will be directed through a single lane in the middle of the construction by temporary traffic lights.
- Additionally, there are three detours set up to detour traffic around the construction zone. Two detours are set up on Peace Road (one in each direction) and there is also a detour on Mary Street (eastbound only).
- Ongoing electrical work as well as grading for sidewalk and boulevard work will take place all week.
|
Week of May 29, 2023
|
- West and East bound traffic on King Street will be directed through a single lane in the middle of the construction by temporary traffic lights.
- Additionally, there are three detours set up to detour traffic around the construction zone. Two detours are set up on Peace Road (one in each direction) and there is also a detour on Mary Street (eastbound only).
- Grading and paving of the north lane (westbound) will take place early in the week. Following this the traffic will be switched to this newly paved lane and crews will work to repair the south lane (eastbound).
|
Week of May 22, 2023
|
- West and East bound traffic on King Street will be directed through a single lane in the middle of the construction by temporary traffic lights.
- Additionally, there are three detours set up to detour traffic around the construction zone. Two detours are set up on Peace Road (one in each direction) and there is also a detour on Mary Street (eastbound only).
- The road excavation on the North Side of King Street between Sturgeon Road North, along with installation of road granulars to take place during the week.
- Concrete curb installation planned on the north side of King Street will occur later in the week.
- All businesses and residences will be accessible for the week.
|
Week of May 8, 2023
|
- West and East bound traffic on King Street will be directed through a single lane in the middle of the construction by temporary traffic lights.
- Additionally, there are three detours set up to detour traffic around the construction zone. Load restrictions on the detours have now been lifted. The detours are set up on Peace Road (one in each direction) and Mary Street (eastbound only).
- The plan for the week is to pave the south side of King Street between James Street and Sturgeon Road (including the intersection). Once this paving is complete the single lane traffic will be moved to the south lane.
- Concrete and asphalt removals will take place following the traffic adjustment and then the crews will begin excavation and storm sewer installation on the north side of King Street as well as Sturgeon Road North.
- All businesses and residences will be accessible for the week.
|
Week of May 1, 2023
|
- West and East bound traffic on King Street will be directed through a single lane in the middle of the construction by temporary traffic lights.
- Additionally, there are three detours for light traffic only until the road restrictions are lifted by the City. Reminder that load restrictions are in place on the detoured routes. The detours are set up on Peace Road (one in each direction) and Mary Street (eastbound only). Reminder that load restrictions are in place on the detoured routes.
- The plan for the week is to pour concrete curb on King Street from Sturgeon Road to James Street on Monday.
- The south lane of King Street from Sturgeon Road to James Street will be graded on Tuesday and paved on Wednesday.
- Once the above is complete we will run the single lane of traffic on the south paved lane and continue to work on the north side of King Street, west of Sturgeon Road.
- All businesses and residences will be accessible for the week.
|
Week of April 24, 2023
|
- West and East bound traffic on King St. will be directed through a single lane in the middle of the construction by temporary traffic lights.
- Additionally, there are three detours for light traffic only until the road restrictions are lifted by the City. The detours are set up on Peace Road (one in each direction) and Mary Street (eastbound only).
- The crews are continuing to work on sidewalk preparations and concrete pouring on both the north side and south side of King Street.
- Storm sewer installations west of Sturgeon Road will continue this week.
- All residents are asked to have patience during the construction as there will be a lot of traffic to deal with in a very narrow, tight work area.
- All businesses and residences will be accessible for the week.
|
Week of April 17, 2023
|
- West and East bound traffic on King St. will be directed through a single lane in the middle of the construction by temporary traffic lights.
- Additionally, there are three detours for light traffic only until the road restrictions are lifted by the City. The detours are set up on Peace Road (one in each direction) and Mary Street (eastbound only).
- The crews are working on the temporary traffic lights as well as temporary sidewalk removal in preparation of permanent sidewalk installation. Underground storm sewer installation will begin very soon.
- All residents are asked to have patience during the construction as there will be a lot of traffic to deal with in a very narrow, tight work area.
- All businesses and residences will be accessible for the week.
|
Week of April 10, 2023
|
- The contractor began to mobilize equipment and signage this week in anticipation of road construction starting on Monday April 17, 2023.
- Road closures and detours will be in place the week of April 17.
|
Week of November 28, 2022
|
- It is GIP’s intention to open the road to two-way traffic on or just before this week. The detours (D1, D2 and D3) will be removed shortly there after.
- Some or most of the parking stalls will still be unavailable to the public as the crews need to access the sidewalk areas to place temporary asphalt in lieu of concrete for the winter months.
- As for the remaining of the 2022 season GIP will clean up the site and remove all unnecessary traffic control and construction signage.
- We hope to be demobilized from the site for the winter within the next couple weeks.
|
Week of November 21, 2022 |
- West bound traffic will remain in a single paved lane travelling through King St. for the week.
- The second lift of base asphalt is planned for mid-week as well as the temporary line painting for winter.
- Sidewalk preparation which may include paving sidewalks or permanent concrete pouring will take place all week.
- Eastbound traffic will remain detoured at Peace Rd (Detour 3), Sturgeon Rd. N. (Detour 2) and Sturgeon Rd. S. (Detour 1) all week.
- All businesses and residences will be accessible for the week.
|
Week of November 14, 2022 |
- West bound traffic will remain in a single paved lane travelling through King St. for the week.
- More base asphalt east of Sturgeon Road North to be placed early in the week.
- The crew will be preparing granular base for more curb and gutter and also sidewalk to be poured later in the week and into the following week.
- Some underground electrical work will be on going as well
- Eastbound traffic will remain detoured at Peace Rd (Detour 3), Sturgeon Rd. N. (Detour 2) and Sturgeon Rd. S. (Detour 1) all week.
- All businesses and residences will be accessible for the week.
|
Week of November 7, 2022 |
- West bound traffic will remain in a single paved lane travelling through King St. for the week.
- Underground work will take place on the South side of King St. from Sturgeon Rd. S. heading west towards George St.
- East bound traffic will remain detoured at Peace Rd (Detour 3), Sturgeon Rd. N. (Detour 2), and Sturgeon Rd. S. (Detour 1) all week.
- All businesses and residences will be accessible for the week.
|
Week of October 31, 2022 |
- West bound traffic will remain in a single paved lane travelling through King St. for the week.
- Underground work will take place on the South side of King St. from Sturgeon Rd. S. heading west towards George St.
- East bound traffic will remain detoured at Peace Rd (Detour 3), Sturgeon Rd. N. (Detour 2), and Sturgeon Rd. S. (Detour 1) all week.
- All businesses and residences will be accessible for the week.
|
Week of October 24, 2022 |
- West bound traffic will remain in a single paved lane travelling through King St. for the week.
- Paving operations planned to take place mid-week to shift Westbound traffic so that upcoming work can occur safely.
- Once the Westbound traffic is shifted the underground crew will begin removals and underground work on the South side of King St. once more closer to the lights at Sturgeon Rd.
- East bound traffic will remain detoured at Peace Rd (Detour 3), Sturgeon Rd. N. (Detour 2), and Sturgeon Rd. S. (Detour 1) all week.
- All businesses and residences will be accessible for the week.
|
Week of October 17, 2022 |
- Removals and underground work to continue on the North side of King St.
- West bound traffic will remain in a single paved lane travelling through King St. for the week.
- East bound traffic will remain detoured at Peace Rd. (Detour 3), Sturgeon Rd. N. (Detour 2), and Sturgeon Rd. S. (Detour 3) all week.
- All business and residences will remain accessible to pedestrians for the week.
|
Week of October 10, 2022 |
- The underground crew has shifted to the North side of King St. to continue with removals and storm sewer work, this work will continue all week.
- West bound traffic will remain in a single lane travelling through King St. for the week.
- East bound traffic will remain detoured at Peace Rd. (Detour 3), Sturgeon Rd. N. (Detour 2), and Sturgeon Rd. S. (Detour 3) all week.
- All business and residences will remain accessible to pedestrians for the week.
|
Week of October 3, 2022 |
- The underground crew should finish installing the storm sewer on the south side of King St. Once complete, they will move the crew to the north side of King St. to begin concrete and asphalt removals for the remainder of the week.
- A single lane paving operation is scheduled to take place mid-week to allow West bound traffic to drive on a hard surface.
- West bound traffic will remain able to go straight through town in a single lane. East bound traffic will remain detoured at Peace Rd. (Detour 3), Sturgeon Rd. N (Detour 2) and Sturgeon Rd. S (Detour 1).
- All businesses and residences will remain accessible to pedestrians for the week.
|
Week of September 26, 2022 |
- Car and light traffic will continue being detoured South at Sturgeon Rd. S via detour D1.
- Removals to continue all week.
- Underground crew to continue storm sewer installation at the East end of the project and process West all week.
- All businesses and residences will be accessible to pedestrians for the week.
|
Week of September 19, 2022 |
|
Week of September 12, 2022 |
- Signage is up.
- Traffic is reduced to one lane.
- Detour routes established.
|
Week of September 5, 2022 |
- The contract with the contractor starts on September 6.
- The public may see signage start to go up and equipment start to deploy this week in downtown Omemee.
- No road closures are expected this week.
- Construction anticipated to start the week of September 12.
|