Kawartha Lakes – Significant work has been completed on the Bobcaygeon Beach Park Redevelopment project over the past month and is projected to continue in January.
The December project updates and activities completed so far include:
- Site rough grading is 90 per cent complete
- Site culverts have been installed
- Electrical trenching is underway with the majority of the conduit to be installed and backfilled by the end of December
- Framing for the Maintenance and Washroom Buildings are now approaching completion
- The Masonry contractor will mobilize and prepare structures for exterior facades and interior masonry walls prior to the end of December
- Site soil and materials continue to be prepped for construction
Projected activities for January 2022 include, but are not limited to:
- Masonry work to advance on Washroom and Maintenance Buildings to include exterior finishes and interior infrastructure
- Site soil and materials to continue being prepped for construction
For further information and project updates, visit the Major Projects page of the municipal website.
-30-