Construction Notice |
The City of Kawartha Lakes will be continuing the reconstruction project on Ellice Street in Fenelon Falls from Clifton Street to Wychwood Crescent.
The scope of this project is to install new underground infrastructure (storm sewer, sanitary sewer and watermain), new sidewalks, curbs, and a new roadway.
The contractor for the project is Green Infrastructure Partners Inc. (GIP)
The work is expected to begin again in April 2025 and is anticipated to be completed with base asphalt by Fall 2025, with the final road surface scheduled in the following spring/summer. Working hours are expected to be 7am to 6pm Monday through Friday, with occasional Saturday work if production is lost due to inclement weather or other factors.
Please use caution when driving or walking through the construction site and be aware that heavy construction equipment will be operating on-site. To make sure you are visible to equipment operators, try to get in the habit of making eye contact with the operators as you are walking or driving near them.
View the Construction Notice
For additional information, or if you have any questions or concerns about the project, please contact:
Project Contacts |