Kirkfield

Below you'll find information for the Major Projects happening in the Kirkfield area. These multi-year projects are Capital Projects that include improvements to parks, facilities, implementing strategies, and more. 

Head Lake Boat Launch

Homewood Park Boat Launch

Otter/Maple Park Boat Launch

Suter Drive Boat Launch


 

Head Lake Boat Launch

The City of Kawartha Lakes, Parks and Recreation division will be completing a capital project for improvements at Head Lake Boat Launch. The project is expected to be complete by July 2026.

Why This Work is Needed:

The current boat launch requires upgrades and improvements to provide safe water access for residents.

Scope of Work:

Upgrades and improvements will include the following amenities:

  • extension of concrete launch
  • addition of riprap (added to the sides of the launch to prevent erosion)
  • cantilevered dock
  • new paving
  • new curbs
Access Impacts:

The boat launch will be securely fenced and off limits to patrons for the duration of construction. Upon completion and final compliance inspection, the boat launch will be accessible for visitors to enjoy.

Contact the Project Team

Christopher Lyon

City of Kawartha Lakes

705-324-9411 extension 2120

clyons@kawarthalakes.ca


 

Homewood Park Boat Launch Replacement and Upgrades

The Homewood Park Boat Launch, located on Balsam Lake at Homewood Park Road and Treewood Lane in Kirkfield is scheduled for replacement and upgrades beginning in 2025.

The planned work includes the following:

  • New precast concrete sections on steel sleeper system for in water launching with poured concrete upland approach to aid with accessibility.
  • Riprap and armour stone will be used for shoreline stabilization.

For further information contact:

Christopher Lyons
Supervisor, Capital and Special Projects
Parks and Recreation, City of Kawartha Lakes
Phone: 705-324-9411 extension 2120

 

Otter/Maple Park Boat Launch Replacement and Upgrades

The Otter/Maple Park Boat Launch, located on Balsam Lake at Otter Road and Maple Avenue in Kirkfield is scheduled for replacement and upgrades beginning in 2025.

The planned work includes the following:

  • New precast concrete sections on steel sleeper system for in water launching with poured concrete upland approach to aid with accessibility.
  • Riprap and armour stone will be used for shoreline stabilization.

For further information contact:

Christopher Lyons
Supervisor, Capital and Special Projects
Parks and Recreation, City of Kawartha Lakes
Phone: 705-324-9411 extension 2120

 

Suter Drive Boat Launch Replacement and Upgrades

The Sutter Drive Boat Launch, located on Head Lake at Suter Drive and Dewberry Lane in Kirkfield is scheduled for replacement and upgrades beginning in 2025.

The planned work includes the following:

  • New precast concrete sections on steel sleeper system for in water launching with poured concrete upland approach to aid with accessibility.
  • Riprap and armour stone will be used for shoreline stabilization.

For further information contact:

Christopher Lyons
Supervisor, Capital and Special Projects
Parks and Recreation, City of Kawartha Lakes
Phone: 705-324-9411 extension 2120

Contact Us

Kawartha Lakes 
P.O. Box 9000, 26 Francis Street
Lindsay, ON, K9V 5R8
Telephone: 705-324-9411
Toll free at 1-888-822-2225
After-hours emergencies: 1-877-885-7337

Ask a question - get fast answers